Construction Daily Report: What to Include, With a Template

A construction daily report records what happened on site each day: weather, manpower by trade, equipment, work completed, deliveries, inspections, visitors, delays, safety observations and photos. Written the same day and signed by the superintendent, it becomes the record you rely on for pay applications, delay claims and disputes, so facts and times matter more than prose.

3 min read Tushar Adsul, Founder and CEO

The daily report is the most boring document on a project until something goes wrong. Then it is the most important one. Here is what I would put in it.

Why does the daily report matter?

What should a daily report include?

Section What to record
Project and date Project name, number, date, report number, author
Weather Conditions, temperature, rain or wind, and whether it stopped work
Manpower Workers and hours by company and trade
Equipment What was on site, working or idle
Work completed Activity, location and quantity, tied to the schedule
Deliveries Material received, supplier, ticket number, any damage
Inspections and tests Inspector, result, follow-up
Visitors Owner, architect, inspectors, with times
Delays and issues What held up work, who it affects, RFI or notice numbers
Safety Toolbox talk topic, observations, incidents, near misses
Photos Tagged to location and activity
Signature Superintendent, the same day

How do you write a daily report that holds up?

  1. Write it the same day. Reconstructed logs carry far less weight.
  2. Use facts, times and numbers, not opinions. "Concrete truck arrived 10:40, ordered for 7:00" beats "supplier late again".
  3. Link delays to notices. If the contract requires written notice of a delay, the daily report should name the notice.
  4. Attach photos with location and time.
  5. Keep one format across every project, so the office can read them quickly.

Daily report template

Copy these rows into your own form:

Field Fill in
Project, number, date, report #
Weather AM, PM, temperature; work stopped? hours lost
Manpower Company, trade, workers, hours
Equipment Item, hours used, idle
Work completed Activity, location, quantity
Deliveries Supplier, material, ticket #, condition
Inspections Inspector, type, result
Visitors Name, company, time in and out
Delays and issues Description, impact, RFI or notice #
Safety Toolbox talk, observations, incidents
Photos Number attached
Signature Superintendent, time

How does Lex help?

Lex, BAU AI's field reporting agent, drafts the daily report from crew check-ins, voice notes, delivery tickets and photos, pulls the weather, and flags anything that looks like a delay that may need notice. The superintendent reviews and signs it. Lex is offered to the founding cohort and is not part of the published plans.

If your superintendents spend their evenings on paperwork, join our US founding cohort and test Lex on one of your jobs.

Tushar Adsul, Founder and CEO, BAU AI

Frequently asked questions

Who writes the daily report? Usually the superintendent or the foreman for each trade, reviewed by the superintendent.

How long should you keep daily reports? At least as long as your contract, warranty and claim periods, and your company's record policy; ask counsel for your state.

Is a daily report the same as a daily log? The terms are used interchangeably. Some companies keep a short log and a fuller report.