Resources / Bids and RFPs
Guide hub, bids and RFPs

How US construction bidding works: ITB vs RFP vs IFB vs CMAR

US owners buy construction through a few solicitation types. An ITB or IFB asks for sealed bids and awards to the lowest responsive, responsible bidder. An RFP weighs price against qualifications and approach, so the lowest price can lose. CMAR selects a construction manager early, largely on qualifications, who later commits to a guaranteed maximum price.

What is the difference between an ITB, IFB, RFP and CMAR?

The name on the cover tells you how the owner will pick a winner, and so what to read first.

SolicitationHow the award is madeTypical useRead first
ITB (invitation to bid)Sealed price; lowest responsive, responsible bidderPublic design-bid-build; GC invitations to subsBid form, instructions to bidders, addenda
IFB (invitation for bids)Federal sealed bidding: public opening, award on price and price-related factors (FAR 14.101)Federal construction with complete documentsBid schedule, FAR clause list, wage determination
RFP (request for proposals)Best value: price traded off against stated non-price factors (FAR 15.101-1); Texas also uses competitive sealed proposalsFederal negotiated work, design-build, complex public workEvaluation factors and their weights
CMAR (construction manager at risk)CM selected through an RFP or RFQ with weighted criteria; contracted price may be a GMPPublic buildings, schools, healthcareSelection criteria, fee and general conditions structure

In Texas, Government Code Chapter 2269 sets these methods for public owners. For CMAR, Subchapter F requires the CM to publicly advertise for trade bids or proposals on all major elements of the work (2269.255). "Solicitation" is the umbrella word, used on SAM.gov for all of them.

What is in a construction bid package?

DocumentWhat it doesCommon standard
Instructions to biddersDeadline, bid security, required forms. Missing one can make the bid non-responsive.AIA A701, owner template
Bid formExactly what to price: base bid, alternates, unit prices, allowancesOwner template
Agreement and general conditionsRisk allocation: time, payment, indemnity, claims, terminationAIA A101/A201, ConsensusDocs 200, EJCDC
Supplementary conditionsProject-specific edits to the general conditions, where risk is usually shiftedProject-specific
SpecificationsProducts, quality, execution, by CSI MasterFormat divisionCSI MasterFormat
DrawingsGeometry and connections; read against the specsA/E set
Bonds, insurance and compliance formsBid security, performance and payment bonds, wage determinations, participation formsFAR 52.228 series, state statutes
AddendaChanges issued before bid day; they control over earlier documentsOwner-issued

What makes a bid non-responsive?

On federal sealed bids, a bid "must comply in all material respects with the invitation for bids" (FAR 14.301). State and local rules are similar. The usual causes:

  • Late, or delivered to the wrong place or portal.
  • Missing or wrong bid security (bid bond form, amount, surety).
  • Addenda not acknowledged.
  • Bid form altered, qualified or incomplete; alternates or unit prices left blank.
  • Required forms missing: wage, participation, affidavits, signatures.

Which clauses should you find first in any package?

These are the terms precon teams commonly check before spending pricing time. Each has its own guide.

FindingWhere it livesWhy it matters
Liquidated damages with no capAgreement (AIA A101 4.5) and supplementary conditionsSchedule slip turns into uncapped cost. LD guide
Broad-form indemnityEdits to A201 3.18 or ConsensusDocs 200 10.1You cover losses you did not cause. Indemnity guide
Pay-if-paid for subsSubcontract form in the packageShifts owner nonpayment risk down the chain
Retainage (retention) termsAgreement and supplementary conditionsCash held to the end of the job
Public compliance termsFAR 52 clause list, wage determinations, participation goalsPrice and responsiveness. Compliance guide

Clara, BAU AI's bids and RFPs agent, scans 1,000+ bid portals for the bids that fit, reads the whole package, flags these risks with page cites, and drafts your Go/No-Go. See Clara at work for one package read end to end.

Guides in this series

Frequently asked questions

Is an ITB the same as an IFB?

In practice, yes: both ask for sealed prices against complete documents. IFB is the federal term under FAR Part 14 sealed bidding; ITB is common on state, local and private work, including GC invitations to subcontractors.

When does the lowest bid lose?

On an RFP or other best-value selection, the owner can pick a higher price if its stated non-price factors justify it. On a sealed bid, the lowest bid loses if it is non-responsive or the bidder is not responsible.

What is a bid bond?

A surety's guarantee that the bidder will sign the contract and provide the required bonds if it wins. The amount is set in the instructions to bidders; on federal work the contracting officer sets it under FAR 28.101-2.

What happens if you miss an addendum?

Addenda control over earlier documents, so you may price the wrong scope, and a missing acknowledgment can make the bid non-responsive. Check for new addenda the day before bid day.

How does CMAR pricing work?

The construction manager is selected early, largely on qualifications and fees, then provides a contracted price that may be a guaranteed maximum price. In Texas public CMAR, the CM must publicly solicit bids or proposals from trade contractors for the major elements of the work.