SAM.gov
Solicitation · federal
SAM.gov is the US government's system for federal contract opportunities and contractor registration; you need an active registration to be awarded federal work.
Federal construction solicitations often arrive as an SF-1442 with attachments and FAR clause lists, and amendments post separately. A bid that does not acknowledge every amendment can be rejected as nonresponsive. SAM.gov, SF-1442
Schedule of values
Financial
A schedule of values (SOV) is the line-item breakdown of the contract sum that the contractor bills against each month.
It is approved before the first pay application, usually organized by CSI division, and billed on AIA G702 and G703. Where the dollars sit in the SOV is an early sign of an unbalanced bid. AIA G702/G703
Scope gap
Risk · scope
A scope gap is work the project requires that no subcontractor bid covers, usually at the seams between trades.
Common zones include moisture mitigation between concrete and flooring, firestopping between MEP and drywall, and controls between mechanical packages. Each unresolved gap becomes a change order or a self-perform cost after award. CSI MasterFormat
Scope of work
Contract
A scope of work is the written description of what a contractor or subcontractor must deliver, including inclusions, exclusions and interfaces with other trades.
Example (illustrative): on a Travis County, TX job, the Division 09 flooring bid and the Division 03 concrete bid both exclude moisture mitigation. Each sub assumed the other carried it, which is a classic scope gap. CSI MasterFormat
Self-performed work
Estimating
Self-performed work is the part of a project a general contractor does with its own crews rather than subcontracting.
Concrete, carpentry and general labor are common examples. Some owners and CMAR rules require competing self-performed packages. Owner procurement rules
Shop drawings
Process
Shop drawings are detailed drawings prepared by a contractor, sub or supplier to show how a part of the work will be fabricated and installed.
They are submittals: the architect reviews them for conformance with the design intent, but they do not change the contract documents. AIA A201-2017 § 3.12
Solicitation
Solicitation
A solicitation is any owner-issued package that invites bids or proposals, including ITBs, RFPs, RFQs and federal SF-1442 packages.
It sets the scope, schedule, contract form and submission rules, and includes instructions to bidders, forms, conditions, specifications, drawings and addenda. It is the first document Clara reads once a bid lands in your inbox, from her portal scan or your own upload.
Submittal
Process
A submittal is the product data, shop drawings, samples or test reports a contractor sends the design team for review before fabrication or installation.
The submittal register is built from Division 01 and each technical section. A late submittal on a long-lead item such as switchgear can move the critical path. AIA A201-2017 § 3.12
Substantial completion
Process
Substantial completion is the stage when the work is complete enough that the owner can occupy or use it for its intended purpose.
It usually stops liquidated damages, starts warranties and triggers release of most retainage. The remaining items go on a punch list. AIA A201-2017 § 9.8
Supplementary conditions
Standard
Supplementary conditions are the owner’s project-specific changes and additions to the general conditions.
They are where owners shift risk: uncapped LDs, shorter notice periods or broader indemnities usually appear here rather than in the standard form. CSI MasterFormat 00 73 00