How to Build a Three-Week Look-Ahead Schedule

A three-week look-ahead breaks the next 15 working days of the master schedule into daily, crew-level activities. Each week, the superintendent and trade foremen update it, check every activity for constraints such as RFIs, submittals, materials, inspections and access, and only commit to work that is ready. Tracking the share of commitments completed shows whether the plan is reliable.

3 min read Tushar Adsul, Founder and CEO

The master schedule tells you where the project should be. The look-ahead tells crews what they will actually do on Monday. Most schedule slips I have seen started as constraints nobody looked at three weeks out.

What is a look-ahead schedule?

A short-interval schedule, usually three weeks, sometimes two to six, built from the master schedule at a finer level of detail. AIA A201-2017 Section 3.10 requires the contractor to prepare and keep a construction schedule current; the look-ahead is how the field keeps that promise week to week.

Master schedule Three-week look-ahead
Horizon Whole project Next 15 working days
Detail Activities and milestones Daily tasks by crew and location
Owner Scheduler or PM Superintendent with trade foremen
Updated Monthly Weekly

How do you build one, step by step?

  1. Pull the next three weeks of activities from the master schedule.
  2. Break each activity down by location, crew and day.
  3. Ask each trade foreman for crew sizes and sequence; their buy-in is the point.
  4. Screen every task for constraints: open RFIs, submittals not approved, material not delivered, inspections not booked, predecessor work not done, access, equipment.
  5. Assign each constraint an owner and a date to clear it.
  6. Commit only to work that is ready for next week.
  7. Review weekly, compare what was done with what was committed, and record why anything slipped.

How do you measure whether the look-ahead works?

The Last Planner System, developed through the Lean Construction Institute, uses percent plan complete (PPC): the share of tasks committed for the week that were finished. Recording the reason for each miss, such as a late submittal or a crew moved to another job, shows which constraints to clear earlier.

What are the common mistakes?

How does Patrick help?

Patrick, BAU AI's project management agent, builds the three-week look-ahead from the master schedule, checks each task against open RFIs, submittals and deliveries, and flags the constraints to clear. The superintendent and the trades adjust and commit. Patrick is offered to the founding cohort and is not part of the published plans.

If your look-ahead lives in a spreadsheet nobody updates, join our US founding cohort and test Patrick on one of your jobs.

Tushar Adsul, Founder and CEO, BAU AI

Frequently asked questions

Why three weeks? It is long enough to clear most constraints, such as a submittal or a delivery, and short enough to plan in daily detail.

Who owns the look-ahead? The superintendent, with input and commitments from each trade foreman.

What is a good PPC? Teams track the trend, not one number. A rising PPC means the plan is becoming reliable.