What is a punch list in construction?

A punch list is the list of items that must be completed or corrected after the work is substantially complete, such as damaged finishes, missing trim or equipment not yet commissioned. The contractor prepares it, the architect adds to it at inspection, and finishing it is a condition of final completion and final payment.

How does a punch list work?

Under A201, when the contractor considers the work substantially complete, it prepares and submits a comprehensive list of items to be completed or corrected. The architect inspects and may add items.

Each item should name its location, the responsible subcontractor and the date due. The certificate of substantial completion often sets the time allowed to finish the list.

Long punch lists usually mean problems were not caught during the job; walking areas as they finish keeps the final list short.

Where is it in the contract documents?

DocumentClauseWhat it says
AIA A201-2017Section 9.8.2Contractor prepares the list of items to complete or correct
AIA G704CertificateSets the time to complete the listed items
AIA A201-2017Section 9.10Final completion and final payment

What does it look like on a project?

At substantial completion of a Travis County, TX school addition, the punch list has 214 items across 38 rooms. Assigned by trade with photos and due dates, all are closed in 26 days, and the final pay application follows.

IllustrativeExample figures, not a real project.

What should you check?

  • Each item has a location, responsible trade, photo and due date
  • The time allowed in the certificate of substantial completion
  • What retainage is held against the list
  • Sign-off by the architect when items are closed
  • Warranty items kept separate from punch items

Patrick, BAU AI's project management agent, tracks this against the schedule and the closeout list. Patrick is offered to the founding cohort.

Frequently asked questions

Who creates the punch list?

The contractor prepares it; the architect inspects and adds items.

Is the punch list part of substantial completion?

It is created at substantial completion and must be finished before final completion and final payment.

What is a rolling punch list?

Checking and closing items area by area as work finishes, instead of in one walk at the end.

Find this clause in your own contract

Bring one contract or bid package to a 15-minute call. The agents read it with you and cite every finding to its clause and page.