Glossary, financial

What is retainage in construction?

Retainage (also called retention) is the part of each progress payment that the owner holds back, often 5 to 10 percent, until the work is substantially complete. It secures the owner against unfinished or defective work, and general contractors usually hold the same percentage back from their subcontractors.

How does retainage work?

Each pay application calculates retainage on work completed and, where the contract says so, on stored materials. The amount builds up over the job and is released at or after substantial completion, often with a smaller amount kept for punch list work.

The rate comes from the contract. On AIA projects it is set in the Agreement, and A201 ties the release to substantial completion. On federal contracts, FAR 32.103 says retainage shall not exceed 10 percent of the approved estimated amount and may be reduced as the job nears completion.

States regulate retainage too. In Texas, on private work where a mechanic's lien can be claimed, Property Code Section 53.101 requires the owner to reserve 10 percent of the contract price, or of the value of the work, during the work and for 30 days after it is completed.

Where is it in the contract documents?

DocumentClauseWhat it says
AIA A101 AgreementArticle 5Sets the retainage percentage and any reduction
AIA A201-2017Section 9.8.5Ties payment of retainage to substantial completion
FAR32.103Federal retainage not to exceed 10 percent of the approved estimate
Texas Property CodeSection 53.101Owner reserves 10 percent on private work during the job and for 30 days after completion

What does it look like on a project?

On a $1,050,000 Austin, TX building contract with 10 percent retainage, $420,000 of work completed and stored to date means $42,000 is held back. If the owner reduces retainage to 5 percent at 50 percent completion, the amount held stops growing at the new rate, and release follows substantial completion and the closeout documents.

IllustrativeExample figures, not a real project.

What should you check?

  • The rate, and whether it applies to stored materials
  • When and how it reduces as the job progresses
  • What triggers release: substantial completion, final completion, closeout documents or lien waivers
  • Whether your subcontract retainage matches the prime contract, so you are not financing the difference
  • State limits on public work where the project is

Fina, BAU AI's finance and budget agent, tracks this from the contract to the pay application, each figure linked to its source. Fina is offered to the founding cohort.

Frequently asked questions

Is retainage the same as retention?

Yes. The terms are used interchangeably in US construction.

What is a typical retainage rate?

Between 5 and 10 percent of each payment is common. Federal contracts cap it at 10 percent (FAR 32.103), and many states cap it on public work.

When is retainage released?

Usually at or after substantial completion, under the contract terms. Some contracts release most of it then and keep a smaller amount until the punch list and closeout documents are done.

Related

Related terms: schedule of values, lien waiver, mechanic's lien, unit price contract, guaranteed maximum price (GMP), allowance, substantial completion, punch list, notice to proceed.

Sources

  • FAR 32.103, Progress payments under construction contracts (acquisition.gov)
  • Texas Property Code Section 53.101, Funds required to be reserved
  • AIA A201-2017, General Conditions of the Contract for Construction, Section 9.8.5

Find this clause in your own contract

Bring one contract or bid package to a 15-minute call. The agents read it with you and cite every finding to its clause and page.