What is a notice to proceed (NTP) in construction?
A notice to proceed (NTP) is the owner's written instruction to the contractor to start work. It usually sets the date the contract time begins, so it starts the clock for completion and liquidated damages. Owners often issue it after the contract is signed and bonds, insurance and permits are in place.
How does a notice to proceed work?
On federal construction, FAR 52.211-10 requires the contractor to start work within the number of calendar days stated after receiving the notice to proceed, and sets completion either as a number of days after the NTP or as a calendar date.
On AIA contracts, the Agreement states the date of commencement, which may be the date of a notice to proceed.
A late NTP compresses the schedule if the completion date is fixed; check whether the contract adjusts time when the NTP slips.
Where is it in the contract documents?
| Document | Clause | What it says |
|---|---|---|
| FAR | 52.211-10 | Commencement, prosecution and completion of work after the NTP |
| AIA A101-2017 | Section 3.1 | Date of commencement |
| Bid documents | Instructions | Expected NTP timing and contract time |
What does it look like on a project?
A federal contract in Texas allows 10 calendar days to start after the NTP and 365 days to complete. The NTP is received on February 2, so work must start by February 12, and the completion date is counted from February 2.
IllustrativeExample figures, not a real project.
What should you check?
- What starts the contract time: NTP, contract date or a stated date
- What must be in place before the NTP: bonds, insurance, permits
- Whether a late NTP extends the time
- Limited or partial NTPs and what they allow
- The liquidated damages start date
Clara, BAU AI's agent for bids and RFPs, flags this in the bid package with the page it is on, so your team decides before pricing.
Frequently asked questions
Does contract time start at signing or at the notice to proceed?
The contract decides. Many start the time at the NTP; AIA forms use the date of commencement stated in the Agreement.
What is a limited notice to proceed?
An NTP that authorizes only part of the work, such as procurement or mobilization, before the full NTP.
Can I start work before the NTP?
Usually not at the owner's cost. Work before the NTP may not be paid or insured.
Related
Related terms: addendum, bid alternate, bid shopping, CSI MasterFormat, allowance, unit price contract, substantial completion, punch list, retainage, lien waiver.
Sources
- FAR 52.211-10, Commencement, Prosecution, and Completion of Work (acquisition.gov)
- AIA A101-2017, Section 3.1
Find this clause in your own contract
Bring one contract or bid package to a 15-minute call. The agents read it with you and cite every finding to its clause and page.