What is a construction change directive (CCD)?

A construction change directive (CCD) is a written order from the owner and architect that directs a change in the work before the owner and contractor agree on its price or time. The contractor proceeds with the work, and the cost is settled later by agreement or, failing that, determined from actual costs.

How does a construction change directive work?

A CCD keeps the job moving when a change cannot wait for negotiation. It is signed by the owner and architect, not necessarily the contractor, which is the key difference from a change order.

If the contractor agrees with the adjustment, it signs the CCD and it becomes a change order. If not, the architect determines the adjustment from the actual cost of the work, such as labor, materials, equipment rental, bond and insurance premiums and supervision, plus a reasonable allowance for overhead and profit.

Because the price is decided after the fact, daily cost tracking on CCD work is what protects the contractor.

Where is it in the contract documents?

DocumentClauseWhat it says
AIA A201-2017Section 7.3Construction change directives
AIA A201-2017Section 7.3.4How cost is determined when there is no agreement
AIA G714FormConstruction Change Directive form

What does it look like on a project?

The owner of a Travis County, TX school addition needs a 2-hour stair enclosure instead of 1-hour after a code review. The architect issues a CCD the same week; the contractor tracks crew hours, material and equipment daily, and the final amount is settled from those records plus the agreed overhead and profit.

IllustrativeExample figures, not a real project.

What should you check?

  • Who must sign: owner and architect, and whether your signature means agreement
  • How the contract measures cost and markup on directed work
  • Daily cost records with backup for every CCD
  • The time impact, requested in writing
  • Notice deadlines if you disagree with the architect's determination

Fina, BAU AI's finance and budget agent, tracks this from the contract to the pay application, each figure linked to its source. Fina is offered to the founding cohort.

Frequently asked questions

What is the difference between a CCD and a change order?

A change order is agreed and signed by owner, contractor and architect. A CCD directs the work before price or time is agreed.

Do I have to perform work under a CCD?

Under A201 Section 7.3, yes: the contractor proceeds with the directed change, and the adjustment is settled later.

How is a CCD priced without agreement?

The architect determines it from actual, documented costs plus a reasonable allowance for overhead and profit, under Section 7.3.4.

Find this clause in your own contract

Bring one contract or bid package to a 15-minute call. The agents read it with you and cite every finding to its clause and page.