What is value engineering in construction?
Value engineering is a structured review that looks for ways to deliver the same function and quality at lower cost, such as a different system, material or detail. On federal work, a contractor can propose changes through a value engineering change proposal and share in the savings if the government accepts it.
How does value engineering work?
Good value engineering compares function, cost and life-cycle impact, not just first cost. Cutting scope or quality is not value engineering; it is a scope change.
Under FAR 52.248-3, Value Engineering for construction, the government's share of net instant contract savings is 45 percent on fixed-price contracts, so the contractor keeps 55 percent; on cost-reimbursement contracts the government keeps 75 percent. Accepting a proposal is the contracting officer's decision.
On private and CM at risk work, value engineering usually happens during design and GMP development.
Where is it in the contract documents?
| Document | Clause | What it says |
|---|---|---|
| FAR | Part 48 and 52.248-3 | Value engineering and the construction VE clause |
| CM at risk agreements | Preconstruction services | VE during design |
| Change order | Accepted proposals | How an accepted change enters the contract |
What does it look like on a project?
On a federal building in Texas, a contractor proposes precast wall panels instead of cast-in-place walls with the same performance, saving $180,000 net. Under a fixed-price contract, the contractor's share is 55 percent, or $99,000.
IllustrativeExample figures, not a real project.
What should you check?
- That function, performance and code compliance are unchanged
- Life-cycle and maintenance costs, not just first cost
- The design and approval time the change needs
- How savings are shared under your contract
- Who carries design responsibility for the change
Clara, BAU AI's agent for bids and RFPs, flags this in the bid package with the page it is on, so your team decides before pricing.
Frequently asked questions
Is value engineering just cutting cost?
No. It keeps the required function and quality at lower cost; cutting scope is a different thing.
How much of the savings does a contractor get?
On federal fixed-price contracts under FAR 52.248-3, the government's share is 45 percent, so the contractor keeps 55 percent of net instant savings.
When does value engineering happen?
Best during design; on hard-bid work, after award through change proposals.
Related
Related terms: construction change directive, differing site conditions, waiver of consequential damages, flow-down clause, builder's risk insurance.
Sources
- FAR Part 48 and FAR 52.248-3, Value Engineering - Construction (acquisition.gov)