What is a flow-down clause in a subcontract?
A flow-down clause binds a subcontractor to the general contractor in the same way the general contractor is bound to the owner, by incorporating the prime contract's terms into the subcontract. It keeps obligations consistent down the chain, but it can also pass the owner's risks to subcontractors who never saw the prime contract.
How does a flow-down clause work?
A201-2017 Section 5.3 requires the contractor, by written agreement, to bind each subcontractor to the terms of the contract documents and to assume toward the contractor the obligations the contractor assumes toward the owner.
Broad flow-down language can pull in the prime contract's notice deadlines, liquidated damages, indemnity and dispute process, which is why subcontractors should ask for and read the prime contract.
Good subcontracts flow down rights as well as obligations, such as time extensions and payment for changes.
Where is it in the contract documents?
| Document | Clause | What it says |
|---|---|---|
| AIA A201-2017 | Section 5.3 | Subcontractual relations: binding subs to the contract documents |
| AIA A401-2017 | Subcontract | Standard form between contractor and subcontractor |
| ConsensusDocs 750 | Subcontract | Standard form subcontract |
What does it look like on a project?
A Texas electrical subcontractor signs a subcontract that flows down the prime contract. Months later it learns the prime contract requires notice of claims within 7 days, not the 21 days in its own subcontract. Because of the flow-down clause, the 7-day limit applies to it too.
IllustrativeExample figures, not a real project.
What should you check?
- Ask for the prime contract before signing
- Notice deadlines and claim procedures that flow down
- Liquidated damages and indemnity passed to you
- Rights that should flow down too: time, change payment, dispute resolution
- Conflicts between the subcontract and the prime contract, and which governs
Dora, BAU AI's contract review agent, reads subcontracts and prime contracts side by side and flags terms that flow down further than they should, cited to the clause.
Frequently asked questions
What does flow-down mean in construction?
That the subcontractor takes on toward the general contractor the same obligations the general contractor has toward the owner.
Should a subcontractor read the prime contract?
Yes. A flow-down clause makes its terms part of your subcontract.
Do rights flow down as well as obligations?
Only if the subcontract says so. Ask for rights such as time extensions and payment for changes to flow down too.
Related
Related terms: construction change directive, differing site conditions, waiver of consequential damages, value engineering, builder's risk insurance.
Sources
- AIA A201-2017, Section 5.3
- AIA A401-2017 and ConsensusDocs 750 standard subcontracts
Find this clause in your own contract
Bring one contract or bid package to a 15-minute call. The agents read it with you and cite every finding to its clause and page.