What is a guaranteed maximum price (GMP) contract?

A guaranteed maximum price (GMP) contract pays the contractor the actual cost of the work plus a fee, up to a ceiling the contractor guarantees. Costs above the GMP are the contractor's risk; savings below it go to the owner or are shared, as the contract says. GMPs are common with construction manager at risk.

How does a guaranteed maximum price work?

The GMP is usually set once design is far enough along, as an amendment to the construction manager's agreement. It is built from the estimated cost of the work, the fee, general conditions and a contractor's contingency, with stated assumptions and clarifications.

Because payment is cost-based, the owner can audit the books. The assumptions and clarifications that come with the GMP decide what counts as a change.

Common forms include AIA A102 (cost of the work plus a fee with a GMP), AIA A133 (construction manager as constructor, with a GMP amendment) and ConsensusDocs 500.

Where is it in the contract documents?

DocumentClauseWhat it says
AIA A102-2017AgreementCost of the work plus a fee with a guaranteed maximum price
AIA A133-2019Exhibit AGMP amendment for construction manager as constructor
ConsensusDocs 500AgreementOwner and construction manager, GMP

What does it look like on a project?

A Texas school district sets a GMP of $5,400,000 with its CM at risk. The final cost of the work plus fee is $5,210,000, so the district pays $5,210,000; if the contract splits savings 50/50, the CM also receives half of the $190,000 below the GMP.

IllustrativeExample figures, not a real project.

What should you check?

  • The assumptions and clarifications behind the GMP
  • What the contractor's contingency may be used for
  • How savings are split
  • What costs are reimbursable and what is in the fee
  • Audit rights and record-keeping requirements

Dora, BAU AI's contract review agent, flags how your contract changes this clause from the AIA base form, cited to the clause and page, for your team and counsel to decide.

Frequently asked questions

Who pays if costs exceed the GMP?

The contractor, unless the overrun comes from an owner change or another event the contract treats as a change.

Is a GMP the same as a lump sum?

No. A lump sum pays a fixed price regardless of cost; a GMP pays actual cost plus fee up to a cap.

When is the GMP set?

Usually during design, once drawings are developed enough to price, as an amendment to the CM agreement.

Find this clause in your own contract

Bring one contract or bid package to a 15-minute call. The agents read it with you and cite every finding to its clause and page.