What is an allowance in a construction contract?
An allowance is a fixed amount written into the contract sum for work or materials that are not fully defined when the contract is signed, such as finish hardware or a carpet the owner has not chosen. When the actual cost is known, the contract sum is adjusted up or down by the difference.
How does an allowance work?
The bid documents state each allowance and its amount, and every bidder carries the same number. Once the owner selects the item, the actual cost is compared with the allowance and a change order adjusts the contract sum.
Under A201, unless the contract says otherwise, an allowance covers the cost of the materials and equipment delivered to the site, less trade discounts. The contractor's costs for unloading, handling, installation, overhead and profit are included in the contract sum, not the allowance.
That split matters: if an allowance turns out to be for a far larger quantity, the installation cost the contractor already carried may not cover it.
Where is it in the contract documents?
| Document | Clause | What it says |
|---|---|---|
| AIA A201-2017 | Section 3.8 | Allowances: what they include and how they are adjusted |
| Specifications | Section 01 21 00 | Allowances, in CSI MasterFormat Division 01 |
| Bid form | Allowance schedule | The amounts every bidder must include |
What does it look like on a project?
A Texas medical office bid carries a $40,000 allowance for door hardware. The owner selects hardware that costs $46,500 delivered. A change order adds $6,500 to the contract sum; installation labor stays in the base price the contractor bid.
IllustrativeExample figures, not a real project.
What should you check?
- What each allowance covers: material only, or material and installation
- Whether overhead and profit on the difference are allowed
- Selection deadlines that could delay the schedule
- How the adjustment is documented: change order with invoices
- Allowances that look too low for the work described
Clara, BAU AI's agent for bids and RFPs, flags this in the bid package with the page it is on, so your team decides before pricing.
Frequently asked questions
Do I add markup to an allowance?
Under A201 Section 3.8, overhead and profit are included in the contract sum, not the allowance. Your contract may say otherwise.
What happens to unused allowance money?
It is credited back to the owner by change order.
Is an allowance the same as a contingency?
No. An allowance is for a known item not yet defined; a contingency is a reserve for unknown events.
Related
Related terms: retainage, schedule of values, lien waiver, mechanic's lien, unit price contract, guaranteed maximum price (GMP), addendum, bid alternate, bid shopping, CSI MasterFormat, notice to proceed.
Sources
- AIA A201-2017, Section 3.8, Allowances
- CSI MasterFormat, Section 01 21 00, Allowances