What is a unit price contract in construction?
A unit price contract pays the contractor a set price for each unit of work actually performed, such as a cubic yard of excavation or a linear foot of pipe, multiplied by the measured quantity. The owner gives estimated quantities for bidding, and the final contract amount follows the quantities actually installed.
How does a unit price contract work?
Bidders price each line of the owner's bid schedule; the total of unit price times estimated quantity decides the low bid. Payment follows measured quantities, so measurement and documentation matter as much as the prices.
When actual quantities differ a lot from the estimate, the unit price may no longer fit. On federal work, FAR 52.211-18 provides an equitable adjustment when an actual quantity varies more than 15 percent above or below the estimated quantity.
Unit pricing is common on highway, utility and site work, where quantities are hard to fix in advance.
Where is it in the contract documents?
| Document | Clause | What it says |
|---|---|---|
| Bid schedule | Line items | Units, estimated quantities and unit prices |
| FAR | 52.211-18 | Equitable adjustment when a quantity varies more than 15 percent |
| Specifications | Measurement and payment | How each unit is measured and paid |
What does it look like on a project?
A Texas county storm sewer bid lists 2,400 linear feet of 24-inch pipe at the bidder's unit price of $118. Field measurement shows 2,610 feet were installed, so the contractor is paid 2,610 times $118, or $307,980, instead of the $283,200 bid total for that line.
IllustrativeExample figures, not a real project.
What should you check?
- How each unit is measured and who measures it
- Quantity variation clauses and their thresholds
- Lines where estimated quantities look wrong, which invite unbalanced bids
- Items paid as lump sum inside a unit price schedule
- Mobilization and other front-end lines
Clara, BAU AI's agent for bids and RFPs, flags this in the bid package with the page it is on, so your team decides before pricing.
Frequently asked questions
What is the difference between a unit price and a lump sum contract?
A lump sum contract pays a fixed price for the defined work; a unit price contract pays per measured unit, so the total moves with actual quantities.
What happens if quantities change a lot?
Many contracts allow a price adjustment beyond a threshold. Federal contracts use 15 percent under FAR 52.211-18.
Why do unit price bids get unbalanced?
A bidder who expects a quantity to grow may raise that unit price and lower others. Owners watch for this when they check bids.
Related
Related terms: retainage, schedule of values, lien waiver, mechanic's lien, guaranteed maximum price (GMP), allowance, addendum, bid alternate, bid shopping, CSI MasterFormat, notice to proceed.
Sources
- FAR 52.211-18, Variation in Estimated Quantity (acquisition.gov)