What is a schedule of values in construction?

A schedule of values is the breakdown of the contract sum into billable lines, such as general conditions, concrete, steel and electrical, that adds up to the full contract amount. Once the architect or owner accepts it, every pay application bills progress against those lines, so it decides how and when the contractor gets paid.

How does a schedule of values work?

The contractor prepares the schedule of values before the first pay application and submits it for acceptance. Each period, the contractor reports work completed and materials stored against each line, and the totals become the amount requested.

Lines should follow how the work is built and inspected, so percent complete can be verified on site. Approved change orders are added as their own lines, so the total always equals the contract sum to date.

Front-loading, putting too much value on early lines, speeds early cash but is a common reason architects reject a schedule of values or a pay application.

Where is it in the contract documents?

DocumentClauseWhat it says
AIA A201-2017Section 9.2Contractor submits a schedule of values allocating the contract sum, used as the basis for payment applications
AIA A201-2017Section 9.3Applications for payment, itemized and supported as the architect requires
AIA G703Continuation sheetThe standard form where the schedule of values is billed each period

What does it look like on a project?

A $1,050,000 Texas building contract might carry eight lines: general conditions $90,000, concrete $150,000, structural steel $180,000, finishes $220,000, plumbing $120,000, HVAC $140,000, electrical $100,000 and a $50,000 approved change order. Mid-job, $420,000 is completed and stored, or 40 percent.

IllustrativeExample figures, not a real project.

What should you check?

  • Lines add up exactly to the contract sum
  • Values match your estimate, not front-loaded
  • Line breakdown matches how the work will be inspected
  • Change orders get their own lines once approved
  • Subcontractor schedules of values roll up into yours

Fina, BAU AI's finance and budget agent, tracks this from the contract to the pay application, each figure linked to its source. Fina is offered to the founding cohort.

Frequently asked questions

Who prepares the schedule of values?

The contractor prepares it and the architect or owner accepts it before the first pay application.

Can the schedule of values change?

Lines can be added for approved change orders. Moving value between existing lines usually needs the owner's or architect's agreement.

Is the schedule of values the same as the G703?

The G703 is the AIA form on which the schedule of values is billed each period. The schedule of values itself is the list of lines and values.

Find this clause in your own contract

Bring one contract or bid package to a 15-minute call. The agents read it with you and cite every finding to its clause and page.