What is a bid alternate in construction?

A bid alternate is a separately priced option in a bid, such as an upgraded roof or a deleted canopy, that the owner may accept or reject when awarding the contract. An additive alternate adds to the base bid and a deductive alternate subtracts from it, letting the owner fit the award to its budget.

How does a bid alternate work?

The bid documents describe each alternate and the bid form has a line for its price. Bidders price the base bid and every alternate.

The solicitation should say how the low bidder is determined, often the base bid plus the alternates the owner selects, sometimes in a stated order. Read that rule closely: an alternate priced carelessly can change who is low.

Alternates are listed in specification Section 01 23 00. Subcontractors must price them too, or the general contractor carries a gap.

Where is it in the contract documents?

DocumentClauseWhat it says
SpecificationsSection 01 23 00Alternates, in CSI MasterFormat Division 01
Bid formAlternates schedulePrice lines for each additive or deductive alternate
Instructions to biddersAward basisHow alternates affect the low bid

What does it look like on a project?

A Travis County, TX school addition has a base bid and two alternates: Alternate 1 adds a covered walkway, Alternate 2 deducts the gym's acoustic panels. Bidder A is low on the base bid, but once the district accepts Alternate 1, Bidder B's total is lower and B is awarded.

IllustrativeExample figures, not a real project.

What should you check?

  • The award rule: how alternates are applied to find the low bidder
  • Each subcontractor priced every alternate
  • Interactions between alternates and the base scope
  • How long the owner can accept an alternate after award
  • Schedule impact of each alternate

Clara, BAU AI's agent for bids and RFPs, flags this in the bid package with the page it is on, so your team decides before pricing.

Frequently asked questions

What is the difference between an additive and a deductive alternate?

An additive alternate increases the base bid if accepted; a deductive alternate reduces it.

Can alternates change who is the low bidder?

Yes. The solicitation states how alternates are applied; the low bidder is often determined on the base bid plus the accepted alternates.

Is an alternate the same as an allowance?

No. An alternate is an option the owner may accept; an allowance is a set amount already in the contract for an undefined item.

Find this clause in your own contract

Bring one contract or bid package to a 15-minute call. The agents read it with you and cite every finding to its clause and page.